UK Fusion Energy opens £115m tender for five STEP system partners

Category: Blankets, Tokamak, Tritium

Computer-generated concept of the STEP tokamak cut in half to show its cross-section and plasma, the plant the five STEP system partner lots will support.
Computer-generated concept of the STEP tokamak cut in half to show its cross-section and plasma, the plant the five STEP system partner lots will support.

The breeder blanket and control system partners will take on detailed design and supply chain contracting for their systems

(Image courtesy of UK Fusion Energy)

UK Fusion Energy (UKFE) has opened tenders, due by 29 January 2027, for five STEP system partners with a combined estimated value of £115 million, and the tender notice shows how responsibility divides between the lots. The breeder blanket and control system partners will take on detailed design and supply chain contracting for their systems, while the test operations partner will run UKFE’s test facilities without taking on their detailed design unless instructed.

Five STEP system partner lots worth up to £115m

These lots follow UKFE’s appointment of Tokamak Energy as its first system partner, which will lead on magnets, and are estimated at £20 million each for breeder blanket and fuel cycle, £35 million for test operations, £15 million for control systems and £25 million for systems engineering and whole plant integration. Contracts run to an estimated March 2029, with options for two further one-year extensions to March 2031 that would bring the maximum term to four years, and the £115 million covers expenses and any extension period.

Design duties differ across the system partner lots

UKFE’s strategy describes it as the whole plant integrator, leading overall plant design and delivery and taking the associated risk, and defines system partners as companies specialising in the critical technologies needed for STEP and beyond. The breeder blanket and control system lots carry matching duties, with each partner leading delivery of its own system, from design and integration through manufacture and operation. One covers the breeder blanket system and the other plant control systems across all areas of the plant, and both also manage all engineering data, take responsibility for detailed design of their systems, equipment and components, and contract through the supply chain.

The fuel cycle partner starts in a supporting role before leading delivery of key fuelling and fuel cycle sub-systems, working through embedded resources on complex design integration challenges and delivering large design packages. Systems engineering and whole plant integration sits mainly within the STEP Design Authority and wider integrated project teams, helping the authority define, coordinate and integrate plant systems into a single operational facility during Tranche 2A, the four-year phase that began in April 2025.

Test operations, the largest lot by value, centres on running UKFE’s test facilities and associated test activities, with the data informing the plant design and its safety justification. The partner is not expected to carry out detailed design of the facilities or test rigs unless explicitly instructed, and accountability stays with UKFE for test requirements and engineering intent and with rig suppliers for rig design.

Bids close in January, with awards expected in April

Tenders are due on 29 January, after which UKFE expects to make its award decision on 6 April, with contracts starting on 23 April. Technical quality carries 50% of the award weighting, with price at 30% and social value and economic value at 10% each. Suppliers with a current UKFE contract, including consortium members, subcontractors and advisers, must sign an ethical walls agreement, and no bidder can win more than three lots unless the tender documents say otherwise.

Whoever wins the breeder blanket and control system lots will be responsible for contracting through the supply chain on those systems. UKFE’s strategy, published in April, says its pipeline of opportunities, including those for major system partners, will fill out over the next two years, and its annual report, published in October, places operational plant and plasma operations on site in the 2040s.